Project Description:
DISTRICT 4- CLEANING DRAINAGE STRUCTURES IN AREA "C" (4 SEPARATE CONTRACTS)
This project is for cleaning of drainage systems including drainage structures, pipes and outlets.
Location:
Resident Engineer: Thomas Gordon
Construction Contract Value: $183,045.00
Construction Bid Price: $110,645.00
Initial Construction Estimate: $108,995.00
District: District 4
Current Status: Winter shutdown (as of 02/15/2008)
Additional Info: (as of 02/15/2008)

Contracts (1) Progress
# 34581 -- Construction Contract
Cleaning Drainage Structures. AREA "C" (4 Separate Contracts) Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/13/2004
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Winter shutdown
    Additional Info
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/09/2002
    Project Review Committee PRC Approved 04/14/2003
    Project Status Advertised 09/27/2003
    Project Status Advertised 12/27/2003
    Project Management