Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
HOPKINTON- SOUTHBOROUGH- BRIDGE REPLACEMENT, H-23-004=S-20-008, ROUTE 85 (RIVER STREET) OVER THE SUDBURY RIVER
The project involves the replacement of the Route 85 (River Street) bridge over the Sudbury River, which connects Hopkinton & Southborough. The proposed bridge will have two 12 foot travel lanes and one 6 foot shoulder and one 8 foot shoulder with a sidewalk on the west side. The superstructure design will incorporate provisions for identified future utilities.
Location:
  • Town of Hopkinton
  • Town of Southborough
  • Resident Engineer: Edmilson Tavares
    Construction Contract Value: $3,815,626.00
    Construction Bid Price: $3,339,745.25
    Initial Construction Estimate: $3,339,461.00
    District: District 3

    Contracts (8) Progress
    # 32171 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract D Final
    # 54837 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 57725 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 57728 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 58998 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Program. Final
    # 64300 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68382 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 71227 -- Construction Contract
    Bridge Replacement (H-23-004=S-20-008) (PCSCS Beams) - Route 85 (River Street) over the Sudbury River. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/18/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/17/2002
    Project Review Committee PRC Approved 04/14/2003
    Project Review Committee Letter 05/19/2003
    Project Status Advertised 09/24/2011
    Project Management
    25% Design 25% Package Received 05/07/2007
    25% Design 25% Package Received 03/26/2010
    25% Design 25% Package Received 08/24/2010
    25% Design 25% Package Comments to DE 07/06/2010
    25% Design 25% Package Comments to DE 07/06/2010
    25% Design 25% Package Comments to DE 07/06/2010
    25% Design Design Public Hearing 10/14/2010
    75% Design 75% Package Received 03/11/2011
    75% Design 75% Package Comments to DE 05/16/2011
    Final Design PS&E Received 08/11/2011
    Final Design PS&E to FAPRO 09/21/2011
    Consultant Contract Process Scope to DE 02/09/2009
    Consultant Contract Process NTP Issued 09/02/2009
    Consultant Contract Process Workhours Approved 05/12/2009