Project Description: |
PETERSHAM- BRIDGE BETTERMENT, P-08-001, ROUTE 32 & 122 OVER THE EAST BRANCH OF THE SWIFT RIVER
The project will replace the superstructure of the existing bridge with new spread prestressed concrete beams and 8" concrete deck with asphalt riding surface. Minor adjustments will be made to the abutments and wingwalls. Staged construction with alternating one-way traffic under the control of traffic signals will be used.
|
Location: |
|
Resident Engineer: | Brian Misterka |
Construction Contract Value: | $1,968,089.00 |
Construction Bid Price: | $1,638,659.00 |
Initial Construction Estimate: | $1,632,714.00 |
District: | District 2 |
|