PETERSHAM- BRIDGE BETTERMENT, P-08-001, ROUTE 32 & 122 OVER THE EAST BRANCH OF THE SWIFT RIVER
The project will replace the superstructure of the existing bridge with new spread prestressed concrete beams and 8" concrete deck with asphalt riding surface. Minor adjustments will be made to the abutments and wingwalls. Staged construction with alternating one-way traffic under the control of traffic signals will be used.
Location:
  • Town of Petersham
  • Resident Engineer: Brian Misterka
    Construction Contract Value: $1,968,089.00
    Construction Bid Price: $1,638,659.00
    Initial Construction Estimate: $1,632,714.00
    District: District 2

    Contracts (3) Progress
    # 36567 -- Design -- Bridge Rehab/Recon/New Const
    Provide design services for the rehabilitation of existing bridges, structural evaluations and emergency design support services. Final
    # 54834 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 57045 -- Construction Contract
    Bridge Reconstruction Br. No. P-08-001 (Concrete) Routes 32 & 122 (Barre Road) over the East Branch of the Swift River Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/15/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/20/2002
    Project Review Committee PRC Approved 04/14/2003
    Project Review Committee Letter 05/19/2003
    Project Status Advertised 09/06/2008
    Project Management
    100% Design 100% Package Received 11/06/2007
    100% Design 100% Plans Complete 06/20/2008
    25% Design Design Public Hearing 09/11/2007
    Final Design PS&E Received 08/20/2008
    Final Design PS&E to FAPRO 09/02/2008
    Consultant Contract Process Scope to DE 06/24/2005
    Consultant Contract Process NTP Issued 06/30/2005
    Consultant Contract Process Workhours Approved 06/24/2005