Project Description:
MANSFIELD- BRIDGE REPLACEMENT, M-03-003 & M-03-045, BALCOM STREET OVER THE WADING RIVER
This project includes the replacement of two adjacent bridges on Balcom Street over the Wading River. The bridges will be closed during construction and a detour will be in place. A temporary pedestrian bridge may be required.
Location:
  • Town of Mansfield
  • Construction Begins: Autumn 2023
    Resident Engineer: Sean Darling
    Construction Bid Price: $2,959,170.00
    District: District 5
    Current Status: Complete bridge closure in full effect; local traffic only. Base and binder completed . Installing HWY guard rail. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Roadway closed to traffic. Detour in place. (as of 11/18/2024)

    Contracts (3) Progress
    # 123775 -- Construction Contract
    Bridge Replacement, M-03-003 & M-03-045, Balcom Street over the Wading River 77% Complete
    # 32177 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract J Final
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 10/19/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Complete bridge closure in full effect; local traffic only. Base and binder completed . Installing HWY guard rail. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Roadway closed to traffic. Detour in place.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/02/2003
    Project Review Committee PRC Approved 04/14/2003
    Project Status Advertised 08/19/2023
    Project Management
    100% Design 100% Package Received 10/17/2022
    100% Design 100% Package Comments to DE 11/18/2022
    100% Design 100% Plans Complete 12/13/2022
    25% Design 25% Package Received 04/20/2020
    25% Design 25% Package Approved 10/07/2021
    25% Design Design Public Hearing 01/25/2021
    25% Design 25% Plans Complete 02/24/2022
    75% Design 75% Package Received 05/06/2022
    Final Design PS&E Received 01/23/2023
    Final Design PS&E Received - Resub 1 02/17/2023
    Final Design PS&E Received - Resub 2 05/19/2023