MANSFIELD- BRIDGE REPLACEMENT, M-03-003 & M-03-045, BALCOM STREET OVER THE WADING RIVER
This project includes the replacement of two adjacent bridges on Balcom Street over the Wading River. The bridges will be closed during construction and a detour will be in place. A temporary pedestrian bridge may be required.
Location:
  • Town of Mansfield
  • Construction Begins: Autumn 2023
    Resident Engineer: Sean Darling
    Construction Bid Price: $2,959,170.00
    District: District 5

    Contracts (3) Progress
    # 123775 -- Construction Contract
    Bridge Replacement, M-03-003 & M-03-045, Balcom Street over the Wading River 6% Complete
    # 32177 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract J Final
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 10/19/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/02/2003
    Project Review Committee PRC Approved 04/14/2003
    Project Status Advertised 08/19/2023
    Project Management
    100% Design 100% Package Received 10/17/2022
    100% Design 100% Package Comments to DE 11/18/2022
    100% Design 100% Plans Complete 12/13/2022
    25% Design 25% Package Received 04/20/2020
    25% Design 25% Package Approved 10/07/2021
    25% Design Design Public Hearing 01/25/2021
    25% Design 25% Plans Complete 02/24/2022
    75% Design 75% Package Received 05/06/2022
    Final Design PS&E Received 01/23/2023
    Final Design PS&E Received - Resub 1 02/17/2023
    Final Design PS&E Received - Resub 2 05/19/2023