Project Description: |
NEW MARLBOROUGH- BRIDGE REPLACEMENT, BR# N-08-012, HAYES HILL ROAD OVER KONKAPOT RIVER
The proposed project consists of replacing the existing bridge on the same alignment with improvements to the approach roadway.
|
Location: |
|
Resident Engineer: | Stephen Brzezinski![]() |
Construction Contract Value: | $871,706.00 |
Construction Bid Price: | $762,455.55 |
Initial Construction Estimate: | $469,678.00 |
District: | District 1 |
Current Status: | Contractor is working on the punch list items. The road is open to traffic. (as of 09/14/2007) |
Additional Info: | There is a detour from Mill River Road to Clayton Road to Great Barrington Road. (as of 11/21/2006) |
|