Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
NEW MARLBOROUGH- BRIDGE REPLACEMENT, BR# N-08-012, HAYES HILL ROAD OVER KONKAPOT RIVER
The proposed project consists of replacing the existing bridge on the same alignment with improvements to the approach roadway.
Location:
  • Town of New Marlborough
  • Resident Engineer: Stephen Brzezinski
    Construction Contract Value: $871,706.00
    Construction Bid Price: $762,455.55
    Initial Construction Estimate: $469,678.00
    District: District 1
    Current Status: Contractor is working on the punch list items. The road is open to traffic. (as of 09/14/2007)
    Additional Info: There is a detour from Mill River Road to Clayton Road to Great Barrington Road. (as of 11/21/2006)

    Contracts (1) Progress
    # 48168 -- Construction Contract
    New Marlborough - Hayes Hill Road over Knokapot River (N-08-012) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 10/05/2006
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Contractor is working on the punch list items. The road is open to traffic.
    Additional Info
    There is a detour from Mill River Road to Clayton Road to Great Barrington Road.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/02/2003
    Project Review Committee PRC Approved 04/14/2003
    Project Review Committee Letter 05/19/2003
    Project Status Advertised 08/27/2005
    Project Management
    100% Design 100% Package Received 05/20/2005
    100% Design 100% Package Comments to DE 06/24/2005
    25% Design 25% Package Received 08/14/2003
    25% Design 25% Package Approved 12/23/2003
    25% Design Design Public Hearing 05/05/2004
    75% Design 75% Package Received 11/01/2004
    75% Design 75% Package Comments to DE 12/10/2004
    Final Design PS&E Received 07/12/2005
    Final Design PS&E to FAPRO 07/22/2005
    Consultant Contract Process Scope to DE 01/02/2003
    Consultant Contract Process NTP Issued 02/19/2003
    Consultant Contract Process Workhours Approved 02/07/2003