Project Description:
DISTRICT 5- CONTRACT 5C (CAPE COD AND MARTHA'S VINEYARD) - MAINTENANCE OF STATE HIGHWAYS
Location:
Design Responsibility: In-House Boston
Right of Way Responsibility: MassDOT
Project Manager: David Rock
Estimated Total Federal Participating Construction Cost: N/A
District: District 5
Current Status: This project has been advertised for construction bids. (as of 04/12/2003 )

Contracts (0) Progress
No contracts associated with this project

Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/15/2003
    Project Status Advertised 04/12/2003