| Project Description: |
DISTRICT 5- COLD PLANING AND RESURFACING AT VARIOUS LOCATIONS IN AREA B
|
| Location: | |
| Resident Engineer: | Daniel Vieira![]() |
| Construction Contract Value: | $5,363,416.32 |
| Construction Bid Price: | $4,439,676.17 |
| Initial Construction Estimate: | $4,019,390.00 |
| District: | District 5 |
|
Bridges |
||||||||
|
||||||||||
|
|
|
|||||||||||||||||||||||||||||