TYNGSBOROUGH- RELOCATION OF ROUTE 113 (PAWTUCKET BOULEVARD)
The work on this project will include the relocation of Pawtucket Boulevard for a distance of approximately 3700 linear feet from just south of the Colony Heights condominium complex driveway northerly to the existing Tyngsborough Bridge over the Merrimack River. The roadway will vary in width from 2-4 travel lanes with additional turning lanes at the intersections. It is anticipated that the two realigned intersections will be signalized. At least a 4’ continuous shoulder should be provided in each direction to accommodate bicyclists.
Location:
  • Town of Tyngsborough
  • Resident Engineer: Brian Polley
    Construction Contract Value: $5,251,231.20
    Construction Bid Price: $4,650,207.99
    Initial Construction Estimate: $7,035,462.50
    District: District 4

    Contracts (5) Progress
    # 34039 -- Design -- Highway
    Tyngsborough - relocation of Pawtucket Boulevard (Route 113), work includes the reconstruction of the Pawtucket Boulevard/Sherburne Avenue and Frost Road intersections. Final
    # 54827 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 57915 -- Design -- Services
    Work will consist of providing engineering design services to the MassHighway on an open end basis for Layout and Right of Way assignments. Final
    # 64316 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68142 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Route 113 (Pawtucket Boulevard) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/29/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/30/2003
    Project Review Committee PRC Tabled 11/18/2003
    Project Review Committee PRC Tabled 06/22/2004
    Project Review Committee PRC Tabled 04/21/2005
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee Letter 02/01/2006
    Project Status Advertised 09/18/2010
    Project Management
    100% Design 100% Package Received 12/23/2008
    100% Design 100% Package Comments to DE 02/23/2009
    25% Design 25% Package Received 04/29/2005
    25% Design 25% Package Comments to DE 09/20/2005
    25% Design Design Public Hearing 11/17/2005
    75% Design 75% Package Received 05/04/2007
    75% Design 75% Package Comments to DE 12/12/2007
    Final Design PS&E Received 08/26/2010
    Final Design PS&E to FAPRO 09/08/2010
    Consultant Contract Process NTP Issued 05/21/2004