| Project Description: |
NORWOOD- SHARON- WALPOLE- RESURFACING AND RELATED WORK ON A SECTION OF ROUTE 1
The work under this contract consists of resurfacing the roadway, replacing the existing traffic signal loop detectors, and rebuilding the drainage along Route 1 NB & SB in the Towns of Sharon, Walpole and Norwood for a distance of 7.1 miles.
|
| Location: |
|
| Resident Engineer: | Brian Lewis![]() |
| Construction Contract Value: | $3,854,369.85 |
| Construction Bid Price: | $2,932,905.00 |
| Initial Construction Estimate: | $3,079,600.00 |
| District: | District 5 |
|
Bridges |
||||||||
|
||||||||||
|
|
|
|||||||||||||||||