Project Description: |
DUXBURY- MARSHFIELD- COLD PLANING & RESURFACING ON A SECTION OF ROUTE 3A
|
Location: |
|
Design Responsibility: | In-House Boston |
Right of Way Responsibility: | MassDOT |
Project Manager: | Albert Li![]() |
Estimated Total Contract Cost: | $2,579,049.74 |
Estimated Total Federal Participating Construction Cost: | N/A |
District: | District 5 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges |
|
|
|