Project Description:
DISTRICT 5- FENCE BETTERMENT AT VARIOUS LOCATIONS
Location:
Resident Engineer: Charles Hodges Jr
Construction Contract Value: $768,627.00
Construction Bid Price: $721,827.30
Initial Construction Estimate: $743,158.00
District: District 5

Contracts (1) Progress
# 41766 -- Construction Contract
603829 District 5 - Fence Upgrades at Various Locations Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/15/2005
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/07/2003
    Project Review Committee PRC Approved 04/14/2003
    Project Status Advertised 04/09/2005
    Project Management
    Final Design PS&E Received 04/05/2005
    Final Design PS&E to FAPRO 04/05/2005