| Project Description: |
WESTFORD- BRIDGE REPLACEMENTS, BR# W-26-008, ROUTE 225 OVER STONY BROOK & W-26-024, ROUTE 225 OVER MURRAY PRINCE RACEWAY
This proposed project will result in the reconstruction of two bridges, an upgraded railroad crossing, and a reconfigured intersection.
|
| Location: |
|
| Resident Engineer: | Patrick Marion![]() |
| Construction Contract Value: | $1,124,570.00 |
| Construction Bid Price: | $992,336.50 |
| Initial Construction Estimate: | $684,525.00 |
| District: | District 3 |
|