ADAMS- BRIDGE REPLACEMENT, A-04-002, LEONARD STREET OVER DRY BROOK
Location:
  • Town of Adams
  • Resident Engineer: Thomas Tierney
    Construction Contract Value: $1,145,860.00
    Construction Bid Price: $990,700.00
    Initial Construction Estimate: $873,578.52
    District: District 1
    Current Status: Project is complete. (as of 01/14/2009)

    Contracts (3) Progress
    # 32175 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract H Final
    # 53594 -- Construction Contract
    Adams - Bridge Construction (A-04-002) - Leonard Street over Dry Brook Completed
    # 58594 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final

    Bridges

    Contract Dates
    Notice to Proceed: 03/14/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Project is complete.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/10/2003
    Project Review Committee PRC Approved 04/14/2003
    Project Status Advertised 09/02/2006
    Project Management
    100% Design 100% Package Received 06/15/2006
    100% Design 100% Package Comments to DE 07/27/2006
    25% Design 25% Package Received 03/07/2005
    25% Design 25% Package Comments to DE 04/22/2005
    25% Design Design Public Hearing 06/07/2005
    75% Design 75% Package Received 11/23/2005
    75% Design 75% Package Comments to DE 04/10/2006
    Final Design PS&E Received 08/09/2006
    Final Design PS&E to FAPRO 08/09/2006
    Consultant Contract Process NTP Issued 12/13/2003