Project Description:
DISTRICT 4- INSTALLATION OF BRIDGE JOINTS AND RELATED WORK (ESSEX AND MIDDLESEX COUNTIES)
This work consists of site-specific, scheduled routine, non-routine maintenance and emergency repairs of fixed joints and expansion joints on bridge decks.
Location:
Resident Engineer: Robert Huettner
Construction Contract Value: $4,954,989.99
Construction Bid Price: $2,766,390.00
Initial Construction Estimate: $2,186,680.00
District: District 4
Current Status: Work under this contract consists of site specific repairs, scheduled routine maintenance ,non routine maintenance and emergency repairs of fixed joints and expansion joints on bridge decks. (as of 10/15/2007)
Additional Info: This project is now substansially complete. (as of 10/15/2007)

Contracts (1) Progress
# 34585 -- Construction Contract
Installation of Bridge Joints and Related Work. (Middlesex & Essex Counties) (2 Separate Contracts) Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/24/2004
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Work under this contract consists of site specific repairs, scheduled routine maintenance ,non routine maintenance and emergency repairs of fixed joints and expansion joints on bridge decks.
    Additional Info
    This project is now substansially complete.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/31/2003
    Project Review Committee PRC Approved 04/14/2003
    Project Status Advertised 11/29/2003