Project Description: |
COLRAIN- REHABILITATION AND RELATED WORK ON GREENFIELD ROAD
The project begins at the Shelburne Town Line and ends at the Route 112 bridge over the North River, a distance of 3.1 miles. The project consists of pavement milling, overlay and some areas of reconstruction. Drainage structures will be repaired, new pavement markings will be applied and traffic signs will be replaced where needed.
|
Location: |
|
Resident Engineer: | John Bedard |
Construction Contract Value: | $824,486.66 |
Construction Bid Price: | $687,814.72 |
Initial Construction Estimate: | $832,420.00 |
District: | District 1 |
Current Status: | Project is complete except for punch list items. (as of 12/14/2006) |
|
Bridges |
|
|
|
|