Project Description:
COLRAIN- REHABILITATION AND RELATED WORK ON GREENFIELD ROAD
The project begins at the Shelburne Town Line and ends at the Route 112 bridge over the North River, a distance of 3.1 miles. The project consists of pavement milling, overlay and some areas of reconstruction. Drainage structures will be repaired, new pavement markings will be applied and traffic signs will be replaced where needed.
Location:
  • Town of Colrain
  • Resident Engineer: John Bedard
    Construction Contract Value: $824,486.66
    Construction Bid Price: $687,814.72
    Initial Construction Estimate: $832,420.00
    District: District 1
    Current Status: Project is complete except for punch list items. (as of 12/14/2006)

    Contracts (1) Progress
    # 43015 -- Construction Contract
    The project is a mill and overlay project to replace the distressed pavement wearing course of the entire three miles of Greenfield Road and short adjacent pieces of Main Road Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/06/2005
    Contract Information
    Project Designer: Municipality
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Project is complete except for punch list items.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/02/2003
    Project Review Committee PRC Approved 04/14/2003
    Project Review Committee Letter 05/19/2003
    Project Status Advertised 06/25/2005
    Project Management
    Final Design PS&E Received 05/25/2005
    Final Design PS&E to FAPRO 06/23/2005