Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
MONTAGUE- RESURFACING AND RELATED WORK, MILLERS FALL ROUTE 63
The work to be done consists of resurfacing and related work on a section of Route 63 in Montague. The project begins just north of Lake Pleasant Road and proceeds northerly on Route 63 to just north of Bangs Street in the Village of Millers Falls. The Route 63 bridge over the B&M Railroad and its recently paved approaches are not included in this project. The total project length is about 1.8 miles.
Location:
  • Town of Montague
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: Albert Li
    Estimated Total Contract Cost: $651,284.50
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 2
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    No TIP Data Available For This Project