MONTAGUE- MILLERS FALLS STREETSCAPES I AND II, RTE 63- (FEDERAL ST., BRIDGE RD.) EAST AND WEST MAIN ST.
This work consists of streetscape enhancements along West and East Main, Federal, and Bridge Streets in the village of Millers Falls. Also included are the construction of new sidewalks with improvements and stone masonry walls, the installation of period lighting, and the provision of minor drainage improvements, curbing, and pavement markings and signage.
Location:
  • Town of Montague
  • Resident Engineer: Daniel Boucher
    Construction Contract Value: $961,133.00
    Construction Bid Price: $913,184.50
    Initial Construction Estimate: $793,376.00
    District: District 2
    Current Status: Physical work complete (as of 01/04/2007)

    Contracts (1) Progress
    # 38773 -- Construction Contract
    Landscaping and roadside enhancements in the Village of Millers Falls in the Town of Montague. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/02/2005
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Physical work complete
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/04/2003
    Project Review Committee PRC Approved 04/14/2003
    Project Review Committee Letter 05/19/2003
    Project Status Advertised 09/18/2004
    Project Status Advertised 12/11/2004
    Project Status Advertised 12/18/2004
    Project Management
    100% Design 100% Package Received 07/14/2004
    100% Design 100% Package Comments to DE 10/05/2004
    100% Design 100% Plans Complete 10/22/2004
    25% Design 25% Package Received 07/17/2003
    25% Design 25% Package Comments to DE 09/16/2003
    25% Design Design Public Hearing 09/29/2003
    25% Design 25% Plans Complete 09/25/2003
    75% Design 75% Package Received 01/23/2004
    75% Design 75% Package Comments to DE 07/12/2004
    75% Design 75% Plans Complete 07/14/2004
    Final Design PS&E Received 11/24/2004
    Final Design PS&E to FAPRO 08/17/2004
    Final Design PS&E to FAPRO 11/24/2004