Project Description: |
MONTAGUE- MILLERS FALLS STREETSCAPES I AND II, RTE 63- (FEDERAL ST., BRIDGE RD.) EAST AND WEST MAIN ST.
This work consists of streetscape enhancements along West and East Main, Federal, and Bridge Streets in the village of Millers Falls. Also included are the construction of new sidewalks with improvements and stone masonry walls, the installation of period lighting, and the provision of minor drainage improvements, curbing, and pavement markings and signage.
|
Location: |
|
Resident Engineer: | Daniel Boucher |
Construction Contract Value: | $961,133.00 |
Construction Bid Price: | $913,184.50 |
Initial Construction Estimate: | $793,376.00 |
District: | District 2 |
Current Status: | Physical work complete (as of 01/04/2007) |
|
Bridges |
|
|
|
|