Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
MIDDLEBOROUGH- INTERSECTION IMPROVEMENTS, ROUTE 28 AND ROUTE 105
The proposed project site in Middleboro is along Rte. 105 (0.15 mi +/-) and along Rte. 28 (0.16 mi +/-). The intersection will be 4 lanes wide. The proposed project consists of cold planing, leveling, resurfacing and a new traffic signal installation. Also included are new signs, pavement markings, grading, driveway aprons, sidewalks, wheelchair ramps, granite curb, edging, berm, and other incidental items.
Location:
  • Town of Middleborough
  • Resident Engineer: Kenneth White
    Construction Contract Value: $723,513.07
    Construction Bid Price: $490,771.44
    Initial Construction Estimate: $493,230.00
    District: District 5

    Contracts (1) Progress
    # 44351 -- Construction Contract
    Middleborough - Intersection Improvements at Rte 28 (E&W Grove Streets) & Rte 105 (S main Street) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/15/2006
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/04/2003
    Project Review Committee PRC Approved 04/14/2003
    Project Status Advertised 08/20/2005
    Project Management
    100% Design 100% Package Received 01/31/2005
    100% Design 100% Package Comments to DE 03/29/2005
    25% Design 25% Package Received 03/22/2001
    25% Design 25% Package Comments to DE 08/08/2002
    25% Design Design Public Hearing 04/28/2003
    75% Design 75% Package Received 04/02/2004
    75% Design 75% Package Comments to DE 12/13/2004
    Final Design PS&E Received 08/04/2005
    Final Design PS&E to FAPRO 08/04/2005