DARTMOUTH- PADANARAM BRIDGE CAUSEWAY RECONSTRUCTION, D-04-002, BRIDGE STREET OVER APPONAGANSETT RIVER
The Padanaram Causeway Rehabilitation project includes roadway, drainage, structural, and lighting improvements along Gulf Road from the eastern edge of Apponagansett Park to the Padanaram Bridge and Smith Neck Road from Gulf Road southerly approximately 400 feet.
Location:
  • Town of Dartmouth
  • Construction Begins: Spring 2016
    Resident Engineer: Alfredo Nunez
    Construction Bid Price: $8,274,790.95
    District: District 5

    Contracts (1) Progress
    # 90575 -- Construction Contract
    Padanaram Bridge Causeway Reconstruction and Related Work (Including Rehabilitation of Masonry Walls and Br. No. D-04-002) along a Section of Gulf and Smith Neck Roads. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 05/17/2016
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/01/2003
    Project Review Committee PRC Tabled 11/18/2003
    Project Review Committee PRC Tabled 06/22/2004
    Project Review Committee PRC Tabled 03/09/2005
    Project Review Committee PRC Tabled 12/01/2005
    Project Review Committee PRC Approved 06/08/2006
    Project Status Initiated 04/01/2003
    Project Status Advertised 09/12/2015
    Project Management
    100% Design 100% Package Received 02/27/2015
    100% Design 100% Package Comments to DE 06/02/2015
    25% Design 25% Package Received 05/22/2009
    25% Design 25% Package Received 04/05/2011
    25% Design 25% Package Comments to DE 09/24/2009
    25% Design 25% Package Comments to DE 10/19/2012
    25% Design Design Public Hearing 09/11/2014
    75% Design 75% Package Received 02/27/2015
    75% Design 75% Package Comments to DE 06/02/2015
    Final Design PS&E Received 08/06/2015
    Final Design Peer Review Comments to DE 09/10/2015
    Final Design PS&E to FAPRO 09/08/2015