CONCORD- BRIDGE REHABILITATION, BR# C-19-003, SUDBURY ROAD OVER SUDBURY RIVER (HEATH'S BRIDGE)
The roadway work involves full depth reconstruction of approximately 130 feet of bridge approach roadway. Roadway reconstruction entails improvements to the pavement, curbing, sidewalks and highway guardrails. The bridge concrete deck will be replaced with a concrete deck and bituminous concrete overlay. The proposed bridge will match the width of the existing bridge and will consist of 2 travel lanes and 2 sidewalks. One lane will remain open during construction and a temporary signal will be installed at both ends to control bi-directional traffic movement.
Location:
  • Town of Concord
  • Resident Engineer: Jay Patel
    Construction Contract Value: $1,559,628.00
    Construction Bid Price: $1,386,624.30
    Initial Construction Estimate: $1,235,833.00
    District: District 4
    Current Status: The contractor has completed the major items of work on the project. (as of 10/24/2008)

    Contracts (1) Progress
    # 44875 -- Construction Contract
    Concord - Sudbury Road over the Sudbury River, Bridge (C-19-003) Rehabilitation, PF # 603906 Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/02/2006
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    The contractor has completed the major items of work on the project.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/07/2003
    Project Review Committee PRC Approved 04/14/2003
    Project Review Committee Letter 02/20/2004
    Project Status Advertised 10/15/2005
    Project Management
    100% Design 100% Package Received 07/18/2005
    100% Design 100% Package Comments to DE 08/30/2005
    75% Design 75% Package Received 04/22/2004
    75% Design 75% Package Comments to DE 06/09/2005
    Final Design PS&E Received 08/17/2005
    Final Design PS&E to FAPRO 08/17/2005
    Consultant Contract Process NTP Issued 07/03/2003