BOSTON- MILTON- QUINCY- BTV OPERATORS FOR THE HOV LANE/I-93
Location:
  • City of Boston
  • Town of Milton
  • City of Quincy
  • Resident Engineer: Robert Ward
    Construction Contract Value: $816,490.00
    Construction Bid Price: $741,240.00
    Initial Construction Estimate: $753,000.00
    District: District 4

    Contracts (1) Progress
    # 34658 -- Construction Contract
    HOV Lane Barrier Transfer Service Contract. (MHD-HOV 10) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/19/2004
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/23/2003
    Project Review Committee PRC Approved 11/18/2003
    Project Review Committee Letter 11/24/2003
    Project Status Advertised 04/24/2004
    Project Management
    Final Design PS&E Received 04/20/2004
    Final Design PS&E to FAPRO 04/20/2004