WESTFIELD- WEST SPRINGFIELD- ROUTE 20 COLD PLANING AND RESURFACING
The project begins at Westfield Station 69+40 and proceeds easterly along Route 20 to station 117+12.64=5+08.85, and continues to West Springfield Station 50+45, for a total length of 1.76 miles.
Location:
  • City of Westfield
  • Resident Engineer: Michael McCabe
    Construction Contract Value: $1,333,033.00
    Construction Bid Price: $1,094,758.15
    Initial Construction Estimate: $1,063,069.00
    Total Estimated Project Cost: $1,333,033.00
    District: District 2
    Current Status: Project is physically complete (as of 09/18/2006)

    Contracts (1) Progress
    # 38793 -- Construction Contract
    Work includes cold planing and repaving the existing Rte 20 within proje limits and adjacent side streets. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/03/2005
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Project is physically complete
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/30/2003
    Project Review Committee PRC Approved 11/18/2003
    Project Status Advertised 09/25/2004
    Project Management
    Final Design PS&E Received 04/02/2004
    Final Design PS&E to FAPRO 07/08/2004