| Project Description: |
DISTRICT 4- INSTALLATION OF FIBER OPTIC CABLE & COMPLETION OF THE COMMUNICATION NETWORK ALONG I-95/RTE 128 BETWEEN ROUTE 2 & ROUTE 3 NORTH (PHASE I)
The purpose of this project is to install a fiber optic link from Node 1/Route 2 along I-95/Route 128 northbound to the Route 2 interchange in Lexington and use existing MassDOT fiber from the Route 2/Route128 interchange to the Transportation Operations Center.
|
| Location: | |
| Resident Engineer: | Michael Bartolo![]() |
| Construction Contract Value: | $898,826.70 |
| Construction Bid Price: | $2,906,249.30 |
| Initial Construction Estimate: | $1,987,906.70 |
| District: | District 4 |
|
Bridges |
||||||||||||||
|
||||||||||
|
|
|
||||||||||||||||||||||||||||||||