Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WINCHENDON- RESURFACING AND RELATED WORK ON A SECTION OF ROUTE 140 (GARDNER ROAD)
The work includes milling and resurfacing of a section of Route 140 beginning at the Gardner/Winchendon town line and proceeding northerly approximately 2.14 miles to Teel Road. Other work to be done on this project includes adjusting and rebuilding of drainage structures, pavement markings, guardrail end treatments, and other incidental items.
Location:
  • Town of Winchendon
  • Resident Engineer: William Whiteman
    Construction Contract Value: $551,410.50
    Construction Bid Price: $538,910.50
    Initial Construction Estimate: $569,700.00
    District: District 2
    Current Status: Physical work complete. (as of 09/08/2005)

    Contracts (1) Progress
    # 34616 -- Construction Contract
    Resurfacing and Related Work on a Section of Route 140. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/20/2004
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Physical work complete.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 05/02/2003
    Project Review Committee Letter 08/05/2003
    Project Status Advertised 11/01/2003
    Project Management