Project Description:
LUDLOW- WILBRAHAM- BRIDGE RECONSTRUCTION, L-16-003=W-35-001, MILLER STREET & COTTAGE AVENUE OVER CHICOPEE RIVER
Location:
  • Town of Ludlow
  • Town of Wilbraham
  • Resident Engineer: Joseph Hogan
    Construction Contract Value: $2,956,017.00
    Construction Bid Price: $2,680,925.00
    Initial Construction Estimate: $2,041,272.00
    District: District 2
    Current Status: Physical work complete. (as of 11/21/2006)
    Additional Info: Bridge open to traffic (as of 11/21/2006)

    Contracts (1) Progress
    # 39147 -- Construction Contract
    Ludlow-Wilbraham - Bridge Repairs and Related Work on Bridge # L-16-003=W-35-001 Miller Street over the Chicopee River Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/26/2005
    Contract Information
    Project Designer: Municipality
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Physical work complete.
    Additional Info
    Bridge open to traffic
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/02/2004
    Project Review Committee PRC Tabled 11/18/2003
    Project Review Committee PRC Denied 12/03/2003
    Project Status Advertised 09/25/2004
    Project Management
    Final Design PS&E Received 09/08/2004
    Final Design PS&E to FAPRO 09/08/2004