DISTRICT 4- INSTALLATION OF POST-INTERCHANGE DISTANCE SIGNING (4 CONTRACTS)
The project will include the necessary contract specifications (including detail sheets and traffic management plans), and preliminary estimates, for the installation of post-interchange distance sign panels, conforming to current MassHighway and MUTCD standards, at all expressway and freeway interchanges within Districts 4.
Location:
Resident Engineer: Reginald Jacobs Jr
Construction Contract Value: $229,500.00
Construction Bid Price: $178,300.00
Initial Construction Estimate: $268,150.00
District: District 4
Current Status: The project is substansially complete. Final inspections were held on September 6, 2005 and September 7, 2005. A punch list has been generated for final completion. All punch list items are minor and should be completed shortly. (as of 09/13/2005)

Contracts (1) Progress
# 39619 -- Construction Contract
Installation of Information Signs at Various Locations, District 4 Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/25/2005
    Contract Information
    Project Designer: Consultant
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    The project is substansially complete. Final inspections were held on September 6, 2005 and September 7, 2005. A punch list has been generated for final completion. All punch list items are minor and should be completed shortly.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 05/08/2003
    Project Review Committee PRC Approved 11/18/2003
    Project Status Advertised 09/25/2004
    Project Management
    Final Design PS&E Received 02/09/2004
    Final Design PS&E to FAPRO 02/09/2004