MONSON- BRIDGE REHABILITATION, M-27-010, HOSPITAL ROAD OVER CHICOPEE BROOK
The proposed project consists of the construction of a replacement bridge for Hospital Road over Chicopee Brook. The proposed bridge will be a single span structure placed on the existing abutments that will be modified under this contract. In addition, the proposed project will include new bridge rail, safety signing, pavement markings, and other incidental work. The bridge will be closed during construction with a detour for traffic.
Location:
  • Town of Monson
  • Resident Engineer: George Pelletier
    Construction Contract Value: $839,234.00
    Construction Bid Price: $728,395.00
    Initial Construction Estimate: $664,700.00
    District: District 2
    Current Status: Bridge under construction (as of 05/19/2008)
    Additional Info: Bridge closed for the duration of the project. (as of 05/19/2008)

    Contracts (2) Progress
    # 32183 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract P Final
    # 51623 -- Construction Contract
    Monson - Hospital Road over Chicopee Brook Completed

    Bridges

    Contract Dates
    Notice to Proceed: 08/27/2007
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Bridge under construction
    Additional Info
    Bridge closed for the duration of the project.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 05/22/2003
    Project Review Committee PRC Approved 11/18/2003
    Project Review Committee Letter 12/03/2003
    Project Status Advertised 07/15/2006
    Project Management
    100% Design 100% Package Received 11/14/2005
    100% Design 100% Package Comments to DE 04/10/2006
    25% Design 25% Package Received 10/08/2003
    25% Design 25% Package Comments to DE 11/09/2004
    25% Design Design Public Hearing 12/13/2004
    75% Design 75% Package Received 07/11/2005
    75% Design 75% Package Comments to DE 09/01/2005
    Final Design PS&E Received 06/21/2006
    Final Design PS&E to FAPRO 06/28/2006
    Consultant Contract Process NTP Issued 06/11/2003