SOMERVILLE- SIGNAL & INTERSECTION IMPROVEMENTS AT MAGOUN SQUARE (BROADWAY, MEDFORD AND DEXTER STREETS)
This project includes new traffic signals, landscape and streetscape elements, including brick pavers, trees and street furniture.
Location:
  • City of Somerville
  • Resident Engineer: Nicholas Delvento
    Construction Contract Value: $2,065,885.00
    Construction Bid Price: $1,774,696.14
    Initial Construction Estimate: $2,365,316.10
    District: District 4

    Contracts (1) Progress
    # 59993 -- Construction Contract
    Intersection Construction and Related Work at Broadway and Medford Streets (Magoun Square). (ARRA Project) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/08/2009
    Contract Information
    Project Designer: Municipality
    Funding Source: EMERGENCY RELIEF
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/06/2007
    Project Review Committee PRC Tabled 11/18/2003
    Project Review Committee PRC Tabled 06/22/2004
    Project Review Committee PRC Tabled 04/21/2005
    Project Review Committee PRC Tabled 12/01/2005
    Project Review Committee PRC Tabled 03/09/2006
    Project Review Committee PRC Approved 03/08/2007
    Project Review Committee PRC Denied 06/08/2006
    Project Review Committee Letter 03/21/2007
    Project Status Initiated 02/06/2007
    Project Status Advertised 08/01/2009
    Project Management
    100% Design 100% Package Received 04/16/2009
    25% Design 25% Package Received 06/26/2007
    25% Design 25% Package Comments to DE 10/25/2007
    25% Design Design Public Hearing 12/03/2007
    75% Design 75% Package Received 07/25/2008
    75% Design 75% Package Comments to DE 03/26/2009
    Final Design PS&E Received 06/24/2009
    Final Design PS&E to FAPRO 07/29/2009