Project Description:
DISTRICT 4- BRIDGE CLEANING AND DRAINAGE SYSTEMS MAINTENANCE (NORFOLK & SUFFOLK)
Location:
Resident Engineer: Robert Huettner
Construction Contract Value: $968,290.00
Construction Bid Price: $319,190.00
Initial Construction Estimate: $340,150.00
District: District 4
Current Status: Work under this contract consists of cleaning and flushing of scuppers, gutters, troughs, downspouts, drain inlets, and catch basins; Cleaning and flushing of concrete bridge seats, steel bearing assemblies and structural steel (as of 10/09/2008)
Additional Info: Bridge cleaning was completed in numerous locations on Rte 495 North of Boston. This work was done in Aug. and Sept. of 2008. (as of 10/09/2008)

Contracts (1) Progress
# 41064 -- Construction Contract
Bridge Cleaning and Drainage Systems Maintenance Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/12/2005
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Work under this contract consists of cleaning and flushing of scuppers, gutters, troughs, downspouts, drain inlets, and catch basins; Cleaning and flushing of concrete bridge seats, steel bearing assemblies and structural steel
    Additional Info
    Bridge cleaning was completed in numerous locations on Rte 495 North of Boston. This work was done in Aug. and Sept. of 2008.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 06/10/2003
    Project Review Committee PRC Approved 11/18/2003
    Project Review Committee Letter 11/24/2003
    Project Status Advertised 12/11/2004
    Project Management
    Final Design PS&E Received 08/13/2004
    Final Design PS&E to FAPRO 08/13/2004