ATTLEBORO- BRIDGE REHABILITATION, A-16-018, NORTH MAIN STREET OVER BUNGAY RIVER
The proposed project consists of replacing the existing North Main Street bridge over the Bungay River with a single span steel bridge and reconstruction of approximately 280 feet of roadway approach. There will be a detour throughout the duration of the project. One lane will remain open in the northerly direction.
Location:
  • City of Attleboro
  • Resident Engineer: Rajat Gogoi
    Construction Contract Value: $1,920,661.00
    Construction Bid Price: $1,576,592.93
    Initial Construction Estimate: $2,101,638.00
    District: District 5

    Contracts (1) Progress
    # 67215 -- Construction Contract
    Bridge Replacement (A-16-018) (Steel) – North Main Street (Route 152) over the Bungay River. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 12/24/2010
    Contract Information
    Project Designer: Municipality
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/14/2003
    Project Review Committee Letter 07/28/2003
    Project Status Advertised 09/18/2010
    Project Management
    100% Design 100% Package Received 03/12/2010
    100% Design 100% Package Comments to DE 02/19/2010
    25% Design 25% Package Received 01/29/2003
    25% Design 25% Package Comments to DE 05/23/2005
    25% Design Design Public Hearing 10/20/2008
    75% Design 75% Package Received 05/05/2009
    Final Design PS&E Received 06/22/2010
    Final Design PS&E to FAPRO 09/18/2010
    Consultant Contract Process Scope to DE 02/09/2001
    Consultant Contract Process NTP Issued 04/20/2001