| Project Description: |
ATTLEBORO- BRIDGE REHABILITATION, A-16-018, NORTH MAIN STREET OVER BUNGAY RIVER
The proposed project consists of replacing the existing North Main Street bridge over the Bungay River with a single span steel bridge and reconstruction of approximately 280 feet of roadway approach. There will be a detour throughout the duration of the project. One lane will remain open in the northerly direction.
|
| Location: |
|
| Resident Engineer: | Rajat Gogoi![]() |
| Construction Contract Value: | $1,920,661.00 |
| Construction Bid Price: | $1,576,592.93 |
| Initial Construction Estimate: | $2,101,638.00 |
| District: | District 5 |
|