Project Description: |
BOXFORD- DANVERS- MIDDLETON- ROWLEY- TOPSFIELD- RESURFACING AND RELATED WORK ON I-95
|
Location: |
|
Resident Engineer: | Paul Pascucci |
Construction Contract Value: | $6,088,986.00 |
Construction Bid Price: | $5,434,464.64 |
Initial Construction Estimate: | $5,981,250.00 |
District: | District 4 |
Current Status: | This project is now complete. (as of 02/01/2007) |
|
Bridges |
|
|
|
|