CHICOPEE- RECONSTRUCTION ON CENTER STREET (ROUTE 116)
The work consists of reconstructing Center Street in the City of Chicopee. The project begins at the City Line with Springfield and ends approximately 200 feet north of Hampden Street. The work involves full depth reconstruction of the roadway from the City Line to approximately 700 feet south of 1-391; geometric improvements and installing new traffic signals at the intersection of Center Street, Hampden Street and West Street; and installing a new water main and services for the length of the project and on a section of Plainfield Street and a section of Hampden Street. There is also work on all side streets. The approximate length of the project is 1.12 miles.
Location:
  • City of Chicopee
  • Resident Engineer: Joseph Gaudet Jr
    Construction Contract Value: $3,700,175.00
    Construction Bid Price: $4,654,927.00
    Initial Construction Estimate: $6,745,526.00
    District: District 2

    Contracts (1) Progress
    # 58086 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Center Street (Route 116) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/12/2009
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 07/21/2003
    Project Review Committee PRC Tabled 12/03/2003
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee PRC Denied 06/22/2004
    Project Review Committee Letter 12/06/2005
    Project Review Committee Resubmitted 04/13/2005
    Project Status Advertised 12/13/2008
    Project Management
    100% Design 100% Package Received 05/28/2007
    100% Design 100% Package Comments to DE 05/02/2008
    25% Design 25% Package Received 08/24/2005
    25% Design 25% Package Comments to DE 03/14/2006
    25% Design Design Public Hearing 06/05/2006
    75% Design 75% Package Received 07/11/2006
    75% Design 75% Package Comments to DE 10/31/2006
    Final Design PS&E Received 07/01/2008
    Final Design PS&E to FAPRO 12/09/2008
    Consultant Contract Process NTP Issued 12/06/2005