CONWAY- BRIDGE REPLACEMENT, C-20-003, NORTH POLAND ROAD OVER POLAND BROOK
This project consists of reconstructing one bridge along North Poland Road over the Poland Brook in the Town of Conway. The construction includes the reconstruction of the one town owned bridge at the existing location. Minor roadway widening, reconstruction of the existing pavements as well as drainage improvements will be made.
Location:
  • Town of Conway
  • Resident Engineer: Grant Haywood
    Construction Contract Value: $1,812,977.39
    Construction Bid Price: $1,570,129.00
    Initial Construction Estimate: $1,267,823.75
    District: District 1

    Contracts (5) Progress
    # 32183 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract P Final
    # 57467 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 59589 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge ABP projects. Final
    # 64321 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 70376 -- Construction Contract
    Bridge Replacement (C-20-003) (PPCSPS Units Refabricated) - North Poland Road over Poland Brook. (APB) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 12/05/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/08/2003
    Project Review Committee PRC Approved 11/18/2003
    Project Review Committee Letter 12/03/2003
    Project Status Advertised 08/06/2011
    Project Management
    25% Design 25% Package Received 11/09/2004
    25% Design 25% Package Comments to DE 09/01/2005
    25% Design 25% Package Approved 07/12/2010
    25% Design Design Public Hearing 11/16/2006
    25% Design Design Public Hearing 08/19/2010
    25% Design 25% Plans Complete 07/12/2010
    75% Design 75% Package Received 03/08/2011
    75% Design 75% Package Received 03/21/2011
    75% Design 75% Package Comments to DE 04/26/2011
    75% Design 75% Plans Complete 04/26/2011
    Final Design PS&E Received 06/29/2011
    Final Design PS&E to FAPRO 08/03/2011
    Consultant Contract Process Scope to DE 03/03/2003
    Consultant Contract Process Scope to DE 10/06/2009
    Consultant Contract Process NTP Issued 12/16/2009
    Consultant Contract Process Workhours Approved 01/20/2010