Project Description:
HUDSON- BRIDGE REPLACEMENT, H-25-004, HOUGHTON STREET OVER ASSABET RIVER
This bridge replacement project carries Houghton Street over the Assabet River in the Town of Hudson. Work includes reconstruction of bridge approaches, sidewalks, highway guardrails, pavement markings, loam borrow and seeding, and other incidental work. The bridge will be closed to vehicular/pedestrian traffic during construction. A pedestrian bridge will be constructed for use during construction.
Location:
  • Town of Hudson
  • Resident Engineer: Scott Kallin
    Construction Contract Value: $3,176,880.00
    Construction Bid Price: $2,866,256.67
    Initial Construction Estimate: $3,853,345.00
    District: District 3

    Contracts (6) Progress
    # 57915 -- Design -- Services
    Work will consist of providing engineering design services to the MassHighway on an open end basis for Layout and Right of Way assignments. Final
    # 58595 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 64308 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68940 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final
    # 70963 -- Construction Contract
    Bridge Replacement (H-25-004) (Concrete) - Houghton Street over the Assabet River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 09/25/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/03/2003
    Project Review Committee PRC Approved 11/18/2003
    Project Review Committee Letter 12/03/2003
    Project Status Advertised 09/10/2011
    Project Status Advertised 04/28/2012
    Project Management
    100% Design 100% Package Received 03/04/2011
    100% Design 100% Package Comments to DE 07/18/2011
    25% Design 25% Package Received 02/06/2006
    25% Design 25% Package Comments to DE 01/23/2008
    25% Design 25% Package Comments to DE 12/16/2008
    25% Design Design Public Hearing 02/07/2007
    75% Design 75% Package Received 10/11/2010
    75% Design 75% Package Comments to DE 01/11/2011
    Final Design PS&E Received 08/01/2011
    Final Design PS&E to FAPRO 09/07/2011
    Consultant Contract Process NTP Issued 10/04/2004