Project Description:
WELLESLEY- BRIDGE REPLACEMENT, W-13-015, CEDAR STREET OVER ROUTE 9 WORCESTER STREET
The purpose of this project is to replace the superstructure and center pier of the Cedar Street Bridge over Route 9 in the Town of Wellesley. To facilitate construction while maintaining vehicular and pedestrian traffic, the final bridge width will be increased to four traffic lanes with sidewalks on both sides. The work also includes the reconstruction of about 460 linear feet of Cedar Street and about 500 linear feet of Worcester Road and other incidental work. The Cedar Street/Worcester Road intersection will have new traffic signals. Adequate access to abutting property will be maintained during construction.
Location:
  • Town of Wellesley
  • Resident Engineer: Brian Kelleher
    Construction Contract Value: $4,090,000.00
    Construction Bid Price: $3,450,000.00
    Initial Construction Estimate: $5,300,000.00
    District: District 4

    Contracts (3) Progress
    # 43179 -- Design -- Hwy Eng Open End
    Layout Section requires a consultant to provide the service of Layout plan and written description preparation. Final
    # 59591 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge ABP projects. Final
    # 65281 -- Construction Contract
    Bridge Replacement (W-13-0015) – Cedar Street over Route 9. (DESIGN/BUILD) (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 10/04/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    Design Change
    Design change: Lowered Route 9 clearance from 16.5' to 15'
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/04/2003
    Project Review Committee PRC Approved 11/18/2003
    Project Review Committee Letter 12/03/2003
    Project Status Advertised 01/16/2010
    Project Management
    25% Design 25% Package Received 11/15/2006
    25% Design 25% Package Received 02/17/2010
    25% Design 25% Package Comments to DE 02/19/2010
    25% Design 25% Package Comments to DE 02/19/2010
    25% Design Design Public Hearing 10/27/2009
    Final Design PS&E Received 01/08/2010
    Final Design PS&E to FAPRO 01/11/2010
    Consultant Contract Process Scope to DE 10/21/2003
    Consultant Contract Process NTP Issued 04/15/2005
    Consultant Contract Process Workhours Approved 04/07/2005