Project Description:
FRAMINGHAM- BRIDGE REPLACEMENT, F-07-016, FOUNTAIN STREET OVER MBTA & CSX
The proposed project involves the replacement of the Fountain Street Bridge over the MBTA and CSX Railroad. The project also includes some minor approach work.
Location:
  • Town of Framingham
  • Resident Engineer: Adam Hoey
    Construction Contract Value: $2,759,475.00
    Construction Bid Price: $2,036,250.00
    Initial Construction Estimate: $2,204,089.00
    District: District 3

    Contracts (2) Progress
    # 57734 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 63796 -- Construction Contract
    Bridge Replacement (F-07-016) (Concrete) - Fountain Street over the CSX and MBTA Railroads. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 08/13/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/06/2003
    Project Review Committee PRC Approved 11/18/2003
    Project Review Committee Letter 12/03/2003
    Project Status Advertised 04/10/2010
    Project Management
    100% Design 100% Package Received 05/20/2008
    100% Design 100% Package Received 12/23/2009
    100% Design 100% Package Comments to DE 09/26/2008
    25% Design 25% Package Received 08/01/2005
    25% Design 25% Package Comments to DE 09/15/2005
    25% Design Design Public Hearing 04/06/2006
    75% Design 75% Package Received 02/13/2007
    75% Design 75% Package Received 09/09/2009
    75% Design 75% Package Comments to DE 10/24/2007
    Final Design PS&E Received 02/17/2010
    Final Design PS&E to FAPRO 02/19/2010
    Final Design PS&E to FAPRO 04/02/2010
    Consultant Contract Process Scope to DE 06/16/2004
    Consultant Contract Process NTP Issued 10/04/2004
    Consultant Contract Process Workhours Approved 09/28/2004