Project Description:
HARDWICK- WARE- BRIDGE REHABILITATION, H-08-012=W-05-002, BRIDGE STREET OVER WARE RIVER (AKA - GILBERTVILLE BRIDGE)
The project is in the early design stage with design input being solicited from the Boards of Selectmen and Historic Commissions in both Towns. The draft Preliminary Structures Report, prepared by FS&T for MassHighway, recommends the following: increase the bridge live load to H15 by installing a steel I-beam framing system that runs beneath and along the length of the bridge; install crash-tested safety railings along the interior of the bridge; and use the bridge for alternating one-way traffic. One-way traffic is recommended because the installation of safety railings reduces the roadway width to 16 feet 3 inches roadway, which is too narrow for two-way traffic.
Location:
  • Town of Hardwick
  • Town of Ware
  • Resident Engineer: Mark Shea
    Construction Contract Value: $2,233,996.00
    Construction Bid Price: $1,963,215.00
    Initial Construction Estimate: $2,388,613.26
    District: District 2

    Contracts (3) Progress
    # 32173 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract F Final
    # 57727 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 58220 -- Construction Contract
    Gilbertville Bridge Rehabilitation (H-08-012=W-05-002) (Timber/Steel)-Bridge Street over the Ware River Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/08/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/20/2003
    Project Review Committee PRC Approved 11/18/2003
    Project Review Committee Letter 12/03/2003
    Project Status Advertised 12/27/2008
    Project Management
    100% Design 100% Package Received 05/14/2008
    100% Design 100% Package Comments to DE 07/29/2008
    25% Design 25% Package Received 03/30/2006
    25% Design Design Public Hearing 06/26/2006
    75% Design 75% Package Received 02/07/2007
    75% Design 75% Package Comments to DE 04/24/2007
    Final Design PS&E Received 11/14/2008
    Final Design PS&E to FAPRO 12/23/2008
    Consultant Contract Process NTP Issued 01/28/2004