Project Description:
CHESTER- BRIDGE REHABILITATION, C-11-026, OLD STATE HIGHWAY OVER THE WEST BRANCH OF THE WESTFIELD RIVER
This project will result in the rehabilitation of the existing arch span, the construction of a new arch span on top of the existing span, construction of new wingwalls, and an upgrade of the approaching roadways.
Location:
  • Town of Chester
  • Resident Engineer: Richard Miskinis Jr
    Construction Contract Value: $2,740,764.00
    Construction Bid Price: $2,377,873.00
    Initial Construction Estimate: $2,327,447.00
    District: District 1

    Contracts (3) Progress
    # 32169 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract B Final
    # 57962 -- Construction Contract
    Bridge Rehabilitation (C-11-026) (Concrete) - Old State Highway over the West Branch over the Westfield River Completed
    # 59588 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge ABP projects. Final

    Bridges

    Contract Dates
    Notice to Proceed: 04/22/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/15/2003
    Project Review Committee PRC Tabled 11/18/2003
    Project Review Committee PRC Approved 12/03/2003
    Project Review Committee Letter 01/08/2004
    Project Status Advertised 09/27/2008
    Project Status Advertised 02/14/2009
    Project Management
    100% Design 100% Package Received 09/15/2008
    100% Design 100% Package Comments to DE 12/06/2007
    25% Design 25% Package Received 09/22/2005
    25% Design 25% Package Comments to DE 12/08/2005
    25% Design Design Public Hearing 01/30/2006
    75% Design 75% Package Received 04/25/2006
    75% Design 75% Package Comments to DE 06/20/2006
    Final Design PS&E Received 09/25/2008
    Final Design PS&E to FAPRO 09/23/2008
    Consultant Contract Process Scope to DE 09/09/2003
    Consultant Contract Process NTP Issued 11/12/2003