Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
AMHERST- BRIDGE REHABILITATION, A-08-006, PELHAM ROAD OVER FORT RIVER
The Pelham Road bridge over the Fort River is a two span continuous concrete slab bridge structure constructed in 1926. A newer extension of steel stringers was added to the south to support the sidewalk. The proposed structural work shall consist of replacing the existing deck and sidewalk with a new deck and sidewalk. The bridge profile shall remain essentially unchanged. The curb-to-curb width of the proposed superstructure, and sidewalk width shall also remain essentially the same because of the constraints imposed by adjacent wetlands. This equates to a 24 foot roadway (curb to curb) and one 5 foot 6 inch sidewalk. The substructure will be left in place with the exception of minor modifications to the top portion of the existing bridge abutments, wing walls and associated retaining walls. The superstructure will incorporate provisions for existing utilities. The preservation work shall be done in two stages so the one reversible lane is available to vehicular and pedestrian traffic at all times. A sidewalk will be maintained during construction.
Location:
  • Town of Amherst
  • Resident Engineer: Laura Hanson
    Construction Contract Value: $1,092,931.00
    Construction Bid Price: $963,774.25
    Initial Construction Estimate: $923,687.75
    District: District 2

    Contracts (5) Progress
    # 64300 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64302 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64316 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68382 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 75581 -- Construction Contract
    Bridge Superstructure Replacement (A-08-006) (Concrete) - Pelham Road over the Fort River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 02/01/2013
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/19/2003
    Project Review Committee PRC Approved 11/18/2003
    Project Status Advertised 09/15/2012
    Project Management
    100% Design 100% Package Received 06/12/2012
    100% Design 100% Package Comments to DE 08/01/2012
    25% Design 25% Package Received 07/23/2007
    25% Design 25% Package Received 06/15/2011
    25% Design 25% Package Comments to DE 02/26/2008
    25% Design Design Public Hearing 10/18/2011
    25% Design 25% Plans Complete 09/07/2011
    75% Design 75% Package Received 12/28/2011
    75% Design 75% Package Comments to DE 02/27/2012
    Final Design PS&E Received 08/21/2012
    Final Design PS&E to FAPRO 09/05/2012
    Consultant Contract Process Scope to DE 08/02/2004
    Consultant Contract Process NTP Issued 08/08/2005
    Consultant Contract Process Workhours Approved 08/08/2006