Project Description:
WENHAM- INTERSECTION IMPROVEMENTS ON ROUTE 97 (TOPSFIELD ROAD) AT CHERRY AND MAPLE STREETS
The purpose of this project is to improve the safety and level of service at this intersection. The proposed work includes installation of a traffic signal system responsive to vehicles on all intersection approaches. The signal will include a pedestrian crossing phase. Topsfield Road will be widened to provide separate (opposing) left turn lanes. Sidewalks and wheelchair ramps will be reconstructed. Signs and pavement markings will be updated. Granite curb will be installed. The roadway pavement will be reclaimed or cold planed and resurfaced, depending on pavement design and life cycle cost comparison.
Location:
  • Town of Wenham
  • Resident Engineer: Philip Jodoin
    Construction Contract Value: $1,039,840.00
    Construction Bid Price: $688,400.50
    Initial Construction Estimate: $756,598.50
    District: District 4
    Current Status: A small punchlist is the only wok that remains on this project. (as of 10/30/2008)

    Contracts (2) Progress
    # 53591 -- Construction Contract
    Wenham - Intersection Reconstruction and Related Work on Route 97 (Topsfield Road) at Cherry/Maple Streets Completed
    # 59043 -- Design -- Bridge Open End
    Work will consist of statewide bridge design for the Accelerated Bridge Program on an open end basis. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/31/2008
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    A small punchlist is the only wok that remains on this project.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/25/2003
    Project Review Committee PRC Tabled 11/18/2003
    Project Review Committee PRC Approved 12/03/2003
    Project Review Committee Letter 01/09/2004
    Project Status Advertised 09/01/2007
    Project Management
    100% Design 100% Package Received 01/12/2007
    100% Design 100% Package Received 08/24/2007
    100% Design 100% Package Comments to DE 07/16/2007
    100% Design 100% Package Comments to DE 09/24/2007
    25% Design 25% Package Received 12/14/2004
    25% Design 25% Package Comments to DE 08/08/2005
    25% Design Design Public Hearing 11/14/2005
    75% Design 75% Package Received 04/20/2006
    75% Design 75% Package Comments to DE 06/08/2006
    Final Design PS&E Received 08/10/2007
    Final Design PS&E to FAPRO 08/24/2007