Project Description: |
PALMER- BRIDGE REPLACEMENT, P-01-018, STATE STREET OVER THE WARE RIVER
Work on this project consists of replacing the State Street bridge over the Ware River in Palmer. The proposed bridge will be 26.0 feet wide curb to curb with a 6 foot sidewalk on the west side. The bridge will be closed to vehicular and pedestrian traffic during construction. A detour will be provided.
|
Location: |
|
Resident Engineer: | Michael DeSimone |
Construction Contract Value: | $1,925,709.00 |
Construction Bid Price: | $1,725,554.00 |
Initial Construction Estimate: | $2,528,735.00 |
District: | District 2 |
|