Project Description:
SOUTHWICK- RECONSTRUCTION CONGAMOND ROAD (ROUTE 168), FROM COLLEGE HIGHWAY & ENDS 250 FEET SHORT OF STATE LINE (1.2 MILES)
The purpose of this project is to reconstruct Congamond Road to improve safety by straightening and flattening the roadway and to correct pavement deficiencies caused by poor drainage and normal pavement deterioration. The roadway project begins at College Highway and ends 250 feet short of the state line and currently ends west of town's culvert replacement project across Congamond Road. The roadway project distance is approximately 6,300 feet.
Location:
  • Town of Southwick
  • Construction Begins: Spring 2018
    Resident Engineer: Mark Joy
    Construction Bid Price: $4,134,421.50
    District: District 2

    Contracts (1) Progress
    # 102060 -- Construction Contract
    Roadway Reconstruction and Related Work along (Route 168) Congamond Road. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/22/2018
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/29/2003
    Project Review Committee PRC Tabled 11/18/2003
    Project Review Committee PRC Approved 12/03/2003
    Project Review Committee Letter 01/05/2004
    Project Review Committee Letter 02/07/2007
    Project Status Advertised 08/26/2017
    Project Management
    100% Design 100% Package Received 01/09/2017
    100% Design 100% Package Comments to DE 02/15/2017
    25% Design 25% Package Received 04/29/2005
    25% Design 25% Package Received 10/01/2008
    25% Design 25% Package Received 01/19/2009
    25% Design 25% Package Comments to DE 03/17/2015
    25% Design Design Public Hearing 06/26/2013
    75% Design 75% Package Received 04/19/2016
    75% Design 75% Package Comments to DE 06/03/2016
    Final Design PS&E Received 06/26/2017
    Final Design PS&E to Peer Reviewer 07/13/2017
    Final Design Peer Review Comments to DE 07/24/2017
    Final Design PS&E to FAPRO 08/14/2017
    Final Design PS&E Received - Resub 3 01/08/2018