HADLEY- SIGNAL & INTERSECTION IMPROVEMENTS AT ROUTE 9 (RUSSELL STREET) & ROUTE 47 (MIDDLE STREET)
The purpose of this project is to improve the traffic signals at the intersection of Route 9 and Route 47 in Hadley. A new signal mast arm that extends into the middle of the intersection will improve signal head visibility. Work includes minor roadway widening of the approaches to accommodate four-foot shoulders within the project limits and will transition back to the recently completed Route 9 widening project. Sidewalks will be reconstructed, and wheelchair ramps added.
Location:
  • Town of Hadley
  • Resident Engineer: Joseph Burek
    Construction Bid Price: $3,134,233.00
    District: District 2

    Contracts (4) Progress
    # 34453 -- Design -- Traffic Signing/Signals
    Statewide - provide traffic engineering services in connection with traffic signal improvement projects at statewide state highway locations and to provide engineering service Final
    # 64302 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 90720 -- Construction Contract
    Roadway Reconstruction (Including Signals) at the Intersection of Russell and Middle Streets (Routes 9 and 47). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/30/2016
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 09/11/2003
    Project Review Committee PRC Approved 11/18/2003
    Project Status Initiated 09/23/2005
    Project Status Advertised 09/19/2015
    Project Management
    100% Design 100% Package Received 05/21/2015
    100% Design 100% Package Comments to DE 06/26/2015
    25% Design 25% Package Received 07/14/2004
    25% Design 25% Package Received 02/26/2010
    25% Design 25% Package Comments to DE 12/06/2004
    25% Design 25% Package Comments to DE 07/08/2010
    25% Design 25% Package Comments to DE 02/14/2014
    25% Design Design Public Hearing 06/09/2014
    75% Design 75% Package Received 12/03/2014
    75% Design 75% Package Comments to DE 12/31/2014
    Final Design PS&E Received 08/10/2015
    Final Design Peer Review Comments to DE 08/27/2015
    Final Design PS&E to FAPRO 09/15/2015
    Consultant Contract Process NTP Issued 11/26/2003