AMHERST- RECONSTRUCTION ON ROUTE 116 (WEST ST.) FROM COUNTRY CORNERS RD. TO 800' NORTH OF HAMPSHIRE COLLEGE DRIVE
MassDOT is transferring its ownership of the road to the Town of Amherst so that the town can design the project as local road. The project does include bike path connections, pedestrian accommodation and other amenities at the Atkins Corners location.
Location:
  • Town of Amherst
  • Resident Engineer: Gary Martin
    Construction Contract Value: $7,034,442.00
    Construction Bid Price: $6,060,220.30
    Initial Construction Estimate: $6,811,756.00
    District: District 2

    Contracts (2) Progress
    # 51303 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 66833 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of West Street (Route 116) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/17/2011
    Contract Information
    Project Designer: Municipality
    Funding Source: HIGH PRIORITY PROJECTS
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/04/2003
    Project Review Committee PRC Approved 11/18/2003
    Project Review Committee Letter 03/30/2004
    Project Status Advertised 07/03/2010
    Project Management
    100% Design 100% Package Received 11/03/2009
    25% Design 25% Package Received 03/21/2007
    25% Design 25% Package Comments to DE 06/20/2007
    25% Design Design Public Hearing 06/16/2008
    75% Design 75% Package Received 02/12/2009
    75% Design 75% Package Comments to DE 04/13/2009
    75% Design 75% Plans Approved 04/23/2009
    Final Design PS&E Received 05/25/2010
    Final Design PS&E to FAPRO 07/01/2010