25% Design |
25% Package Received |
11/17/2009 |
25% Design |
25% Package Received |
09/28/2010 |
25% Design |
25% Package Comments to DE |
12/08/2009 |
25% Design |
25% Package Comments to DE |
12/08/2009 |
25% Design |
25% Package Comments to DE |
12/08/2009 |
25% Design |
25% Package Comments to DE |
12/08/2009 |
25% Design |
25% Package Comments to DE |
12/08/2009 |
25% Design |
25% Package Comments to DE |
12/08/2009 |
25% Design |
25% Package Comments to DE |
12/08/2009 |
25% Design |
25% Package Comments to DE |
12/08/2009 |
25% Design |
25% Package Comments to DE |
12/08/2009 |
25% Design |
25% Package Comments to DE |
12/08/2009 |
25% Design |
25% Package Comments to DE |
02/01/2010 |
25% Design |
25% Package Comments to DE |
10/18/2010 |
25% Design |
25% Package Comments to DE |
10/27/2010 |
25% Design |
25% Package Comments to DE |
10/29/2010 |
25% Design |
25% Package Approved |
04/06/2010 |
25% Design |
Design Public Hearing |
05/04/2010 |
25% Design |
25% Plans Complete |
04/06/2010 |
75% Design |
75% Package Received |
01/17/2011 |
75% Design |
75% Package Comments to DE |
02/03/2011 |
75% Design |
75% Package Comments to DE |
02/10/2011 |
75% Design |
75% Package Comments to DE |
02/11/2011 |
75% Design |
75% Package Comments to DE |
02/14/2011 |
75% Design |
75% Package Comments to DE |
03/01/2011 |
75% Design |
75% Package Comments to DE |
03/31/2011 |
Final Design |
PS&E Received |
07/14/2011 |
Final Design |
PS&E to FAPRO |
09/16/2011 |
Consultant Contract Process |
Scope to DE |
09/15/2008 |
Consultant Contract Process |
NTP Issued |
12/16/2008 |