Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
COLRAIN- BRIDGE REPLACEMENT, C-18-023, ROUTE 112 (GRISWOLDVILLE ROAD) OVER GRISWOLDVILLE CANAL
The proposed project involves replacing the current Route 112 bridge over Griswoldville Canal. Work on Route 112 will include roadway reconstruction and resurfacing work. Traffic will not be detoured during any part of the construction process. A traffic management plan utilizing a single lane with alternating flows of traffic will be provided through the installation of traffic control signals.
Location:
  • Town of Colrain
  • Resident Engineer: Grant Haywood
    Construction Contract Value: $880,034.00
    Construction Bid Price: $746,552.00
    Initial Construction Estimate: $972,552.25
    District: District 1

    Contracts (2) Progress
    # 57467 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 66665 -- Construction Contract
    Bridge Replacement (C-18-023) (Concrete) - Route 112 (Griswoldville Road) over Griswoldville Canal (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 12/16/2010
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 09/29/2003
    Project Review Committee PRC Approved 11/18/2003
    Project Review Committee Letter 12/03/2003
    Project Status Advertised 08/07/2010
    Project Management
    25% Design 25% Package Received 07/30/2008
    75% Design 75% Package Received 10/09/2009
    75% Design 75% Plans Approved 10/26/2009
    75% Design 75% Plans Approved 02/04/2010
    75% Design 75% Plans Approved 04/20/2010
    Final Design PS&E Received 07/27/2010
    Final Design PS&E to FAPRO 08/03/2010