GREENFIELD- SIGNAL & INTERSECTION IMPROVEMENTS AT 8 INTERSECTIONS
This project consists of installing new traffic signals, resurfacing, curbing, sidewalks, wheelchair ramps, signs and pavement markings at the following eight intersections in Greenfield: Location 1-- Elm Street at Colrain Street and Solon Street. Location 2-- Conway Street at Allen Street. Location 3-- Deerfield Street at Meridian Street. Location 4-- Deerfield Street at Mill Street and Bank Row. Location 5-- Federal Street at Main Street. Location 6-- Federal Street at Silver Street. Location 7-- High Street at Silver Street. Location 8-- French King Highway at Loomis Street.
Location:
  • Town of Greenfield
  • Resident Engineer: Sean Burke
    Construction Contract Value: $3,229,270.00
    Construction Bid Price: $2,751,337.00
    Initial Construction Estimate: $3,352,605.00
    District: District 2

    Contracts (1) Progress
    # 59051 -- Construction Contract
    Intersection Reconstruction and Related Work at 8 Locations. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/08/2009
    Contract Information
    Project Designer: Municipality
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/03/2003
    Project Review Committee PRC Approved 11/18/2003
    Project Status Advertised 05/09/2009
    Project Management
    100% Design 100% Package Received 11/13/2008
    100% Design 100% Package Comments to DE 02/04/2009
    25% Design 25% Package Received 03/23/2006
    25% Design 25% Package Comments to DE 09/13/2007
    25% Design Design Public Hearing 03/19/2008
    75% Design 75% Package Received 06/10/2008
    75% Design 75% Package Comments to DE 09/18/2008
    Final Design PS&E Received 02/10/2009
    Final Design PS&E to FAPRO 05/06/2009