Project Description:
PITTSFIELD- SIGNAL & INTERSECTION IMPROVEMENTS AT ROUTES 7 & 20 (SOUTH STREET) AT ROUTE 20 (W. HOUSATONIC STREET) & E. HOUSATONIC STREET
This project will install a traffic signal system that will be responsive to vehicles on all intersection approaches. The project will reconstruct sidewalks and wheelchair ramps and update signs and pavement markings. Minor widening will occur at the northbound and southbound approaches of South Street and to the westbound approach of East Housatonic Street. The entire project length is 820 feet on South Street and 490 feet on Housatonic Street.
Location:
  • City of Pittsfield
  • Resident Engineer: Timothy Moore
    Construction Contract Value: $1,109,393.00
    Construction Bid Price: $1,280,492.20
    Initial Construction Estimate: $1,203,027.50
    District: District 1

    Contracts (2) Progress
    # 34453 -- Design -- Traffic Signing/Signals
    Statewide - provide traffic engineering services in connection with traffic signal improvement projects at statewide state highway locations and to provide engineering service Final
    # 55714 -- Construction Contract
    Pittsfield - Intersection Reconstruction and Related Work at Rout 7 (South Street) and Route 20 (Housatonic Street) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/15/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/08/2003
    Project Review Committee PRC Tabled 11/18/2003
    Project Review Committee PRC Approved 12/03/2003
    Project Review Committee Letter 01/05/2004
    Project Status Advertised 09/23/2006
    Project Status Advertised 05/17/2008
    Project Management
    100% Design 100% Package Received 01/22/2007
    100% Design 100% Package Comments to DE 10/19/2007
    25% Design 25% Package Received 01/05/2005
    25% Design 25% Package Comments to DE 04/05/2005
    25% Design Design Public Hearing 05/18/2005
    75% Design 75% Package Received 02/23/2006
    75% Design 75% Package Comments to DE 06/16/2006
    Final Design PS&E Received 10/26/2007
    Final Design PS&E Received 05/09/2008
    Final Design PS&E to FAPRO 10/26/2007
    Final Design PS&E to FAPRO 05/12/2008
    Consultant Contract Process NTP Issued 09/09/2003