Project Description:
WORCESTER- BRIDGE RECONSTRUCTION, W-44-094, (SR 9) BELMONT STREET OVER I-290, INCLUDES PEDESTRIAN BRIDGE
This proposed project in Worcester will replace the bridge carrying Route 9 (Belmont Street) over Interstate 290. The bridge must be replaced due to its non-standard features and deteriorated condition. The proposed bridge will be a two span continuous steel girder structure with a reinforced concrete deck and hot mix asphalt wearing surface. The bridge will be constructed in the same footprint as the existing bridge with the same length. However, the new bridge will be built approximately 15.5 feet wider to the South. The widening is necessary to maintain two lanes of traffic at all times during construction and will allow for the addition of a dedicated left turn lane for turns from Route 9 west bound onto Interstate I-290.
Location:
  • City of Worcester
  • Resident Engineer: Webster Larkin Sr
    Construction Contract Value: $14,647,540.00
    Construction Bid Price: $10,844,817.75
    Initial Construction Estimate: $10,349,705.60
    District: District 3

    Contracts (5) Progress
    # 58213 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 64319 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64323 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 69765 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 82311 -- Construction Contract
    Bridge Superstructure Replacement (W-44-094) (Steel) - Route 9 (Belmont Street) over Interstate 290. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 10/15/2014
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/07/2003
    Project Review Committee PRC Tabled 11/18/2003
    Project Review Committee PRC Approved 12/03/2003
    Project Review Committee Letter 01/08/2004
    Project Status Advertised 05/10/2014
    Project Management
    100% Design 100% Package Received 11/19/2013
    100% Design 100% Package Comments to DE 02/21/2014
    25% Design 25% Package Received 02/11/2009
    25% Design 25% Package Comments to DE 02/07/2012
    25% Design Design Public Hearing 01/31/2013
    75% Design 75% Package Received 06/07/2013
    75% Design 75% Package Comments to DE 07/26/2013
    Final Design PS&E Received 05/06/2014
    Final Design PS&E to FAPRO 05/07/2014
    Consultant Contract Process Scope to DE 04/03/2006
    Consultant Contract Process NTP Issued 09/17/2006