Project Description:
TEWKSBURY- SIGNAL IMPROVEMENTS AT EAST STREET & LIVINGSTON STREET
The project includes the installation of a traffic signal and minor widening and realignment of the roadway edges to provide a new left turn lane on the westbound leg of East Street. A sidewalk will be added along the north-west quadrant of the intersection, which is intended to connect to future sidewalk construction. Wheelchair accessible ramps will be constructed at the north-east and south-west corners.
Location:
  • Town of Tewksbury
  • Resident Engineer: Edward Conley
    Construction Contract Value: $743,547.00
    Construction Bid Price: $631,580.00
    Initial Construction Estimate: $804,596.50
    District: District 4

    Contracts (2) Progress
    # 64304 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68167 -- Construction Contract
    Intersection Improvements and Related Work (Including Traffic Signals) at East and Livingston Streets Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/31/2011
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/27/2003
    Project Review Committee PRC Approved 11/18/2003
    Project Review Committee Letter 11/19/2003
    Project Status Advertised 02/19/2011
    Project Management
    100% Design 100% Package Received 12/22/2010
    100% Design 100% Package Comments to DE 02/09/2011
    25% Design 25% Package Received 08/18/2008
    25% Design 25% Package Comments to DE 12/08/2008
    25% Design 25% Package Approved 08/14/2009
    25% Design Design Public Hearing 01/12/2009
    75% Design 75% Package Received 10/23/2009
    75% Design 75% Package Comments to DE 10/14/2010
    Final Design PS&E Received 02/14/2011
    Final Design PS&E to FAPRO 02/15/2011